Design Sprint Cheat Sheet

Design Sprint is NOT an agile / Scrum sprint. 5-day workshop methodology (Knapp/Zeratsky/Kowitz, Sprint book 2016). For disambiguation see Workshop Sprints vs Agile Sprints.

At a glance

flowchart LR
    R[/readiness/] --> B[/brief/]
    B --> MON[/Monday<br/>map-and-target<br/>~7 hrs/]
    MON --> TUE[/Tuesday<br/>sketch<br/>~7 hrs/]
    TUE --> WED[/Wednesday<br/>decide-and-storyboard<br/>~7 hrs/]
    WED --> THU[/Thursday<br/>prototype-plan + craft build<br/>~9 hrs/]
    THU --> FRI[/Friday<br/>test-and-score + Decider call<br/>~9 hrs/]
    FRI --> CALL{Build /<br/>iterate /<br/>pivot /<br/>stop}

    style R fill:#e1f5ff
    style B fill:#e1f5ff
    style FRI fill:#f0e1ff
    style CALL fill:#ffe1e1

Roles

RoleRequired?Days critical
DeciderYES (load-bearing windows minimum)Mon AM, Wed AM, Fri PM (ideally all 5)
FacilitatorYESAll 5 days
Design leadYESAll 5 days; Tue + Thu critical
Engineering leadYESAll 5 days; Thu critical
PM or ResearcherYESAll 5 days; Friday critical
Customer expert / domain SMERecommendedMon + Fri

Team total: 4-7 people. Smaller fails (“missing perspective on critical days”); larger fails (“decision-making slows”).

Pre-sprint (1-2 weeks before Monday)

  • tool-design-sprint-readiness (30-45 min): Go / Conditional Go / Wait against 8 canonical criteria + customer recruiting plan.
  • tool-design-sprint-brief (60-90 min): two-page scope contract; locks recruiting + medium + format.
  • Customer recruiting (Riley or recruiter; activates day-of-readiness Go): 6 confirmed slots (5 + 1 buffer) by Friday-before-sprint.

Day-by-day timeboxes

Monday (Map and Target; ~7 hrs)

BlockTimeActivityOutput
Welcome09:00-09:30Recap + agenda-
Goal + questions09:30-10:30Long-term goal + sprint questionsOne sentence + 3-7 questions
Map10:30-12:30Customer / system map5-15 step flow
Lunch + first expert12:30-13:30--
Expert interviews13:30-15:302-4 cameos (15-30 min each)Notes
HMW + heat map15:30-16:30Cluster HMW board; heat-voteTop clusters
Target moment16:30-17:00Decider picksSingle target

Tuesday (Sketch; ~7 hrs)

BlockTimeActivityOutput
Welcome09:00-09:15--
Lightning demos09:15-10:453 demos x 3 min per personPattern board
Break10:45-11:00--
Notes + Ideas11:00-12:30Silent independent-
Lunch + recruiting check12:30-13:30--
Crazy 8s13:30-13:408 sketches in 8 min-
Solution Sketch13:40-15:30Silent independent 90 minOne sketch per person
Wrap15:30-17:00Collect + anonymize sketchesWednesday-ready board

Wednesday (Decide and Storyboard; ~7 hrs)

BlockTimeActivityOutput
Welcome + art museum09:00-09:30--
Heat map09:30-09:45Silent dot-voteHot-spot annotations
Speed critique09:45-10:453 min per sketch; sketcher silent”What worries me” notes
Break10:45-11:00--
Straw poll + supervote11:00-11:30Decider supervotesOne sketch (or 2 if rumble)
Storyboard11:30-16:30Build 5-15 panel storyboardThursday build spec
Day-end prep16:30-17:00Thursday roles + assets-

Thursday (Prototype Plan + Craft Build; ~9 hrs)

BlockTimeActivityOutput
Prototype plan09:30-12:00tool-design-sprint-prototype-plan5 roles + Five-Act script + trial-run criteria + participant tracker
Craft build09:30-15:30Maker + Stitcher + Writer + Asset Collector parallelWorking prototype
Mock-run14:00-15:00Interviewer rehearses script-
Trial run15:30-17:00Teammate plays fake customerPASS/FAIL gate
Recovery (if needed)17:00-19:00Fix trial-run failures-

Friday (Test and Score; ~9 hrs)

BlockTimeActivityOutput
Interview 109:00-10:00Five-ActNotes
Interview 210:30-11:30Five-ActNotes
Interview 312:00-13:00Five-ActNotes
Lunch (overlap)13:00-14:00--
Interview 414:00-15:00Five-ActNotes
Interview 515:30-16:30Five-ActNotes
Wrap + hot takes16:30-17:00Silent in parallelOne paragraph per teammate
Decider review17:00-17:30Scorecard + hot takes + callBuild/iterate/pivot/stop
Summary capture17:30-18:00Next-artifact assignmentSprint closed

Decider Checkpoints (do not skip)

MomentWhat the Decider commits to
End of readinessGo verdict + customer recruiting budget
End of briefChallenge + sprint questions + team + recruiting + medium + format
End of Mon (Map and Target)Target moment selection
End of Tue (Sketch)Logistics: sketches collected + attribution stripped + Wed attendance
End of Wed (Decide)Supervote + storyboard build-ready
End of Thu morning (Prototype Plan)Role plan + fidelity bar + script + trial-run criteria
End of FriBuild / iterate / pivot / stop call + next artifact owner

Top 5 failure modes (and recovery)

  1. No customer access for Friday → most common failure. Postpone if recruiting can’t deliver 5+1 by deadline.
  2. Group brainstorming Tuesday → Facilitator enforces silence; if team can’t commit to discipline, methodology is wrong fit.
  3. Consensus drift on Wednesday supervote → Decider’s call is the call; straw poll is input not result.
  4. Thursday prototype slips past 17:00 → 2-hour recovery window; if 19:00 fails, postpone Friday.
  5. Decider hesitates on Friday call → Facilitator forces commitment; “defer” is not an answer.